How to write a roofing change order.

A roofing change order is the written add-on when tear-off or inspection turns up work that was not on the signed contract. It should name the job, tie back to the original agreement, list what you found, price the extra scope on separate lines, and show the new contract total after prior approved changes. This guide walks through a free browser form on Setralynx Studio. It is general paperwork practice, not advice on whether your contract allows the change or how tax belongs on a later invoice. The form has no tax field. If sales tax applies, check with an accountant when you invoice. Dollars in the loaded sample rows are sample data, not a price list.

Start with project and contract fields

Fill project name and address first. Names belong in that line if you need them; there are no separate contractor or homeowner fields. Original contract date or reference holds a contract number or sign date. Roof area or slope reference is free text. The form placeholder (26 squares, 7/12 front, 9/12 rear) shows how to describe a roof, not a real measurement.

Change order date defaults to today on first load and after Clear. Original contract amount and prior approved change orders start at zero. Use a negative prior total when earlier signed changes reduced the contract on balance. There is no change-order number field and no tax field.

Reason dropdown and line items

Common roofing reasons is optional, starting with Select a roofing reason. Presets cover rotted decking, fascia or soffit rot, extra flashing, drip edge or ice-and-water shield, and extra tear-off with dump fee. They are labels you can pick, not a code ruling; local requirements are the inspector's call.

Empty notes get filled from the preset when you pick one; filled notes are not overwritten. On print, notes beat the dropdown if both have text. Each line is description plus one amount, not qty times unit. Add line item adds a blank row at zero. Remove deletes a row. Delete every row and the three sample lines return.

Fresh page sample math ($95 on one line)

Sample lines on load: plywood or OSB sheet installed $95 (sample data), fascia per linear foot $0, tear-off layer and dump fee $0. Sum is $95. At original zero and prior zero, contract total before this change is zero, this change order is $95, revised total is $95. Replace samples before anyone signs. Negative amounts are credits included in the sum.

Worked example: decking and fascia (sample dollars)

Original $18,400 (example), prior $1,250 (example): contract total before this change is $19,650. Keep plywood at $95, set fascia to $180 (example) and tear-off or dump to $225 (example). This change order is $500. Revised contract total is $20,150. Figures are example math, not market rates.

Schedule impact starts at zero. Two days prints Adds 2 days. Zero is No change to the schedule; one is Adds 1 day; more positive days add N days; negatives shorten the schedule by N days. Negative days mean the job may finish sooner.

Credit line and negative prior total

Add unused ridge-vent scope at negative $150 (example) to fresh samples $95, $0, $0. This change order net is negative $55, the net of this sheet only, not a standalone price. With original $18,400 (example) and prior zero, revised total is $18,345.

Prior check: original $10,000 (example) and prior negative $200 (example) give contract total before this change $9,800.

Print, clear, and what stays local

Clear asks Clear everything on this form, then resets fields, today's date, and sample lines. Print or save as PDF uses the browser dialog; pick Save as PDF. The sheet title is Roofing change order, with lines, a This change order row, then original, prior, this change, and revised total. Contract total before this change shows on screen only, not in the print summary. Signature and date lines print blank for contractor and homeowner.

Revised total is original plus prior plus line sum. No deposit field. Nothing uploads. Close the tab and the form is gone. Run the math on the free roofing change order form.

Use it on the next job.

  • Open the free roofing change order form. Enter original contract, prior approved changes, and this change. Revised total updates on the page. Print or save as PDF. Signature lines print blank. Nothing is uploaded. The loaded $95 line is sample data.
  • Browse the $19 kits. Trade templates, instant downloads.
  • See the $497 website. We build a site for a local service business and send the live link before you pay. Keep it for $497 one time, or walk away.