How to write a change order.

A change order is the written record that the job is no longer the job you priced. It says what changed, what it costs, and whether the finish date moves. Without it, extra work is easy to do and easy for the customer to treat as a favour.

What goes wrong without one

The original quote described a bathroom renovation at a fixed price. During demolition you find rot behind the tub, or the customer asks for a larger window. You do the extra work because stopping would waste a day, and you plan to "add it at the end." At invoice time the customer remembers a quick agreement to "take care of it." You remember a price. Those are not the same memory.

That gap is how extras go unpaid. The customer is not always acting in bad faith. Spoken approvals are thin. A change order puts the new scope and the new price on paper before you spend the hours and buy the materials. It does not collect the money for you, and it does not replace a lawyer. It removes the argument about whether the extra was authorized.

This page is general practice for contractors and small shops. Whether your contract requires a particular form, and what happens if you proceed without one, depends on that contract and on local law. If a dispute is already live, talk to a lawyer. Do not treat a template as a court filing.

What every change order needs

A useful change order can be one page. It should still answer the questions a stranger would ask six months later, when nobody remembers the hallway conversation.

If you cannot price the change yet, do not write "rate to follow" and start the work. Name the rate and how time will be recorded, or wait until the price is firm. The signed page is the copy that counts, not a text thread.

Why the revised total matters

Listing only the extra $350, in this example, is half the story. The customer still needs to see the contract they are now in. Original amount, plus prior approved changes, plus this change, equals the revised total. When you invoice, that revised total is the number the bill has to agree with, after deposits already paid.

Example only, not a suggested price: original contract $12,000. One earlier change order added $800 and was signed. This change adds $350 and adds two working days. The revised contract amount is $13,150, and the schedule note says plus two days. The final invoice should be traceable to $13,150, not to a round number you typed from memory.

Credits work the same way. If this change removes $200 of work and adds $350, the net of this change order is $150, and the revised total uses $150, not $350. Write both lines. Customers dispute net figures that hide a credit they thought was larger.

Send it before the work, not after the fight

Stop the extra work. Write the description and the price. Get the signature. Then do the work. If the customer will not sign, do only the original scope. Doing the extra on a promise to sort it out later is how the later invoice goes unpaid.

Keep each change order with the quote it amends. The invoice should name those document numbers and show the revised total, after deposits already paid. Tax on the new total is a question for an accountant. This page does not tell you which tax to charge.

Use it on the next job.

  • Open the free change order form. Enter the original contract, prior changes, and this change. The revised total is calculated on the page, with signature lines, and you can print or save a PDF. Nothing is uploaded.
  • Browse the $19 kits. Trade templates for estimates, invoices, and job sheets, sold as instant downloads.
  • See the $497 website. We build a site for a local service business and send the live link before you pay. Keep it for $497 one time, or walk away.