The schedule collects a price you already set
The quote, contract, or signed change order is where the price lives. The draw schedule only says how that total is collected. If the scope grows, write the change first, with its own price, then update the schedule so the new total and the draws still match. Billing extra from a driveway conversation is how finished work sits unpaid.
Each line needs a name, a trigger, a percent of the contract, the dollar amount that percent makes, and the balance left afterward. The percents should add to 100. A total of 97 leaves part of the contract with no due date. A total of 104 asks for more than the contract. Fix the split before anyone signs.
Name the trigger, not only the week
A date helps both sides plan cash. A trigger says what has to be true before the invoice is fair. "Deposit, due at signing" is a trigger. "Rough-in draw, when the rough inspection is signed off" is a trigger. "Progress payment, around the middle" is a feeling. The customer should be able to look at the work and see whether the condition has happened.
Put the trigger on the same page as the percent. When it is met, the invoice names that line, repeats the amount, and subtracts anything already paid. It should not invent a new percent on the day you want to be paid.
The deposit is the first milestone
A deposit covers the cost of starting: materials you buy before day one, a calendar slot you are holding, or a fee you pay to open the job. Show it as a percent of the same contract total as the later draws. A deposit that sits outside the math makes every later percent look smaller than it is.
How large that first percent should be depends on the job, on what you must spend before the next payment, and on the rules where you work. This is general practice, not legal advice. If you are unsure what you may collect before work starts, ask a lawyer.
Three shapes are common, and they are structures, not recommended rates. A short job can be half at signing and half at completion. A job with a clear middle can be a deposit, a draw when materials arrive or rough-in is done, and a completion draw. A longer job can add a mid-point draw and a last amount held for the punch list. The lines still have to add up to the contract.
A worked example
These figures are an example so the arithmetic is easy to check. They are not a suggested price and not a suggested split.
The contract total is $15,000. The deposit, due at signing, is 30 percent, which is $4,500, leaving $10,500. The rough-in draw, due when the rough inspection passes, is 40 percent, which is $6,000, leaving $4,500. The completion draw, due at substantial completion, is 30 percent, which is $4,500, leaving $0. The percents are 30 + 40 + 30 = 100. The draws are $4,500 + $6,000 + $4,500 = $15,000.
If a signed change order later adds $1,200, the total is $16,200. The same 30/40/30 split, recalculated, is $4,860, then $6,480, then $4,860. You can instead leave the old draws and add one line for the $1,200 only. Show which path you took.
Hold the last amount for a real finish
Substantial completion means the space can be used for its purpose, with a short list of leftovers. Final completion means that list is done. A smaller last draw, due when the punch-list items are finished, gives you a written end and gives the customer a reason to walk the job with you.
Name it in plain language: "Final draw, after the punch-list items on the attached list are done." If the contract calls that hold retainage, follow the contract and ask a lawyer what the word requires where you work.
What belongs on the page you both sign
Write the business name, the client name, the project address, and a reference number that matches the quote. Show the contract total once, at the top. List payment methods you actually accept, and show the balance after each draw. Leave a signature and a date for each party. An unsigned schedule is a suggestion. A signed one is the payment plan you invoice against.
Check with an accountant before you add a tax line. Whether tax sits inside the contract total depends on where you work and on how the quote was written. The schedule does not replace scope or a written change when the work changes. Ask a lawyer if you need to know whether the schedule alone is the whole agreement.