Start with a wage, then load it
The base wage is the hourly pay for the person whose time the rate covers, including an hourly figure you assign to yourself. Payroll burden is the extra percent on that wage for payroll taxes, workers' compensation, and benefits. Burden is a cost of having someone on the tools. It is not profit.
These figures are an example so the arithmetic stays even. They are not a suggested wage or burden. A base wage of $36 an hour with a 25 percent burden is $36 times 1.25, which is $45 of loaded labour per working hour. Ask an accountant which items belong in your burden. This page does not state a typical burden for electricians.
Working hours are not billed hours
Working hours are the hours that person is on the clock for the year. Billable efficiency is the share a customer actually pays for. Driving between jobs, a supply-house run, a permit wait, an inspection, and a callback you did not charge are real work. They never appear on the invoice, so they cannot be the denominator of the rate.
In the same example, 1,600 working hours at 62.5 percent billable is 1,000 billed hours. That percent is not a survey and not a target. It is a split chosen so the hours divide evenly. If your invoices show a different share, use that share. If you have no invoices yet, write the percent down as an assumption and replace it later.
Loaded labour for the year is the loaded rate times working hours, not times billed hours: $45 times 1,600 is $72,000. The 600 unpaid hours are already inside that $72,000. They are recovered when the year's cost is divided by the 1,000 hours you can bill.
Overhead is the van, the licence, and the thin week
Overhead continues when the schedule is thin: the van and fuel you do not bill to one address, insurance, the licence and continuing-education costs, specialized tools, and software. Use your own bills. Materials for a named job usually stay on that job. Folding wire and devices into the hourly rate makes a material-heavy panel look cheap and a labour-only service call look expensive.
The example uses $1,500 a month of overhead, or $18,000 a year. Labour plus overhead is $90,000. Across 1,000 billed hours, break-even is $90 an hour. That covers loaded labour and overhead only. It is not profit, and income tax is not inside it. In this method, tax is set aside from profit, not from wages or overhead. Confirm that with an accountant before you rely on it.
Margin and a tax set-aside sit on top of break-even
Target net margin is the share of billed revenue you want left after the tax set-aside. The set-aside is a percent of profit, not of the whole invoice. The price has to leave that margin after the set-aside comes out of the amount above break-even.
Still an example, not a recommended rate. A 20 percent net margin and a 20 percent tax set-aside make the pre-tax slice of the billed rate 20 percent divided by (1 minus 0.20), which is 25 percent. The recommended rate is break-even divided by (1 minus 0.25): $90 divided by 0.75 is $120 an hour.
On 1,000 billed hours that is $120,000. The $30,000 above the $90,000 of cost is the profit pool. Twenty percent of that pool, $6,000, is the example tax set-aside. The remaining $24,000 is 20 percent of $120,000. If the two percents are so high that the pre-tax slice is the whole rate or more, there is no room left for costs. Lower one of them, and ask an accountant which percent belongs in the tax box. It is a planning input, not a filing position.
A band 15 percent under and 15 percent over the recommended rate only compares a quote with your own number. Here that is $102 to $138. It is not what electricians charge.
The same steps price a crew or a flat job
A helper or a two-person crew uses the same order: combined wage, a burden percent that fits that crew, the working hours for the setup you send, and the overhead that setup carries. Compare the result with the charge-out rate you use now.
A flat price for a panel change or a service call should still contain this labour rate times the hours you expect the visit to take. If the visit runs long, fix the hour estimate on the next quote. Cutting the rate to win the job leaves the unpaid drive and the van payment on fewer billed hours. Sample numbers in the calculator are samples. Replace them. Who may pull a permit, and how payroll is set up, depends on where you work.